Expansion and Rail Loadout

Our team leveraged advanced technology such as 3D scanning, 3D modeling, clash detection software and augmented reality to identify and resolve issues in the design phase, minimizing operational downtime on site. Pre-work planning and management of food safety risks were critical to the success of the project in an operational food facility. The Last Planner System was utilized to dial in weekly, daily and hourly work planning — ensuring a reliable understanding of the shutdown scope, contributions and commitments from trade partners while maximizing momentum leading up to the shutdowns.

The phased project was delivered on time and on budget, with operations resuming as scheduled after each of the three major shutdowns. A total of 94,000 craft hours were logged on site.